The Challenge: Capacity Without Floor Space

Blachprofil 2000, based in Łódź, produces aluminium and steel rain water systems for the residential and commercial construction market in Poland and Germany. By mid-2024, demand for their K-style aluminium gutter had outpaced the output of their existing press line — a 15-year-old machine running at practical capacity with no realistic headroom for volume growth.

The constraint was not just throughput. Their floor was fully committed. Any new equipment had to fit a 22 m × 8 m bay that also housed a packing station and a raw coil buffer — leaving a usable machine envelope of roughly 18 m in length. This ruled out several standard line configurations and required a custom coil handling sequence.

The Blachprofil press bay before installation — coil buffer zone on the left, packing station rear-right.

Specification and Machine Selection

After a site visit and production audit in September 2024, Macring’s projects team proposed a 160-tonne coil-fed hydraulic press line with an integrated servo decoiler and a 7-station forming die. The key specification targets agreed with Blachprofil were:

The 160 T press was selected over the 120 T alternative specifically for its ability to handle the thicker 0.9 mm gauge without exceeding 75% of rated force — a margin our tooling engineers consider the minimum for die longevity in aluminium forming.

Engineering Timeline: 18 Weeks Broken Down

The project was contracted in October 2024 with a factory acceptance test (FAT) deadline of the last week of February 2025. The 18-week schedule was tight but achievable with parallel workstreams:

Phase Duration Milestone
Engineering & die design Weeks 1–4 Drawings approved
Raw material procurement Weeks 2–5 All stock on-site
Press frame & structure Weeks 4–10 Frame assembly complete
Die set machining Weeks 5–12 CMM sign-off
Electrical & PLC build Weeks 8–14 Panel tested
Assembly & tryout Weeks 14–17 Internal FAT
Customer FAT Week 18 Signed acceptance
Die machining — Tampere workshop
Press assembly — week 15

Factory Acceptance and First-Part Results

Blachprofil’s production manager and quality engineer attended the FAT in Tampere on 24 February 2025. The line ran a 2-hour continuous trial at 0.7 mm AA3105-H14 material. Key results against contractual targets:

Output rate: 15.2 parts/min (target ≥ 14)
Profile dimensional accuracy: all 12 check dimensions within ±0.15 mm
Scrap rate during trial: 0.28% (target ≤ 0.4%)
Changeover to 150 mm profile: 22 minutes (no contractual target, noted for reference)

The acceptance certificate was signed on the same day. Installation in Łódź is scheduled for April 2025 with our commissioning engineer on-site for 6 days.

"We were sceptical about the 18-week commitment. Macring hit every milestone and the first-part quality was better than our existing machine after 10 years of tool wear."

Tomasz Wiśniewski, Production Manager, Blachprofil 2000 Sp. z o.o.